There’s Always Something
Our plan was to get as much done on the house before we took a little vacation to see family at Christmas time. It was a good plan, but there were a few hiccups. Kitchen The kitchen cabinets were finally delivered and we jumped on getting them installed. We knew we were going to tile the kitchen floor so we lifted the cabinets with a 3/4” board to give us enough room to lay the Duroc and the tile. This is an important step! If we didn’t lift the cabinets the dishwasher wouldn’t fit correctly under the countertops. Now everything is level and if the dishwasher needs maintenance we can pull it out easily. With all our prep done we were ready to go. There were a few challenges: -the wall oven cabinet couldn’t be lifted so we had to get creative with the toe kick (we will eliminate the toe kick and have the cabinet face go from floor to ceiling) -the gas range valve had to be placed in a different position due to HVAC ducts (we bought a longer hose to reach the valve on the rang...